An inherent strength of Polyphase Systems Ltd is the ability to undertake and successfully complete all projects on time, a consistency with the company’s strategic direction and objective.
We have worked in conjunction with the Ministry of Energy (MOE), Kenya Power & Lighting Co. Ltd (KPLC) and the recently established Rural Electrification Authority (REA) to successfully construct over 180km of 66kv, 33kv, 11kv and 415 volts in distribution lines in over 10 years.
With construction of over 650 distribution substations and connecting over 3000 consumers to the power grid, our vision in brining development to Kenya cannot be questioned. With support received from MOE, REA & KPLC we have built a solid relationship across the country making us one of the top and most successful companies in this field.
CLIENT |
PROJECT NAME AND DESCRIPTION |
Kenya Power & Lighting Co. Ltd |
Last Mile Connectivity Project (Lot 6) – Contract No.A 40
Design and survey, procurement and supply of all line materials, LV accessories, Protection, Conductors and all the necessary installation works & commissioning tests to the customers in Lot 6- Wajir, Mandera & Marsabit – 284km. Over 5,200 customers connected. |
Gammon India Ltd c/0 KPLC |
Contact IX: design, supply and construction of 11&33kv lines in Western Kenya
Construction of 11 &33kv lines in Western Kenya Region on concrete and wooden poles – 25km of HV & 15km LV |
Gammon India Ltd c/0 KPLC |
Energy Sector Recovery Programme
Construction of 66,33 & 11kv lines within Nairobi
Nairobi North – 66kv double single circuit (15km)
Gigiri Line Ext – 11kv (2.3km)
Gigiri Line Ext – 66kv (0.3km)
Athi River SS Line – 66kv (3.5km) |
Ministry of Energy |
Supply and Installation of 33kv & 11kv lines
Distribution & substation on a turnkey basis
Distances – 33kv – 255km
-11kv – 298km
– 415v -169km |
Kenya Power & Lighting Co. Ltd |
Rural Electrification Distribution Lines
Distances – 33kv – 38km
– 11kv -103km
– 415V – 61km |
Kenya Power & Lighting Co. Ltd |
11kv distribution lines & substation in Western Province
Distances – 11kv – 3km
– 415V – 1km |
Kenya Power & Lighting Co. Ltd |
33kv and 415V Distribution lines & substation in Coastal areas
Distances – 33kv – 44km
– 415v – 5km |
Kenya Power & Lighting Co. Ltd |
11kv and 415V Distribution lines & substation in Rift Valley
Distances – 11kv – 27km
– 415v – 13km |
Kenya Power & Lighting Co. Ltd |
33kv Transmission Lines – 11kv & 415V
Distribution lines in Central Province
Distances – 33kv – 68km
– 11kv – 28km
– 415v – 15km |
Kenya Power & Lighting Co. Ltd |
33kv,11kv Transmission lines in Mount Kenya Region
Distances – 33kv – 68km
– 11kv – 28km
415v – 15km |
Kenya Power & Lighting Co. Ltd |
33kv,11kv Transmission lines in Mount Kenya Region
Distances – 33kv – 17km
415v – 21km |
Kenya Power & Lighting Co. Ltd |
11kv Distribution lines & substation in Coffee Factories
Distances – 11kv – 28km
-415v – 6km |
SIEMENS SAS, France |
Lake Turkana Wind Power Project – 33kv line for Collection Grid
Procurement & Supply of 33KV Hardware Materials, Installation of 33KV Network and commissioning of lines in the grid – 150km |